Finke River crossing
The Finke River follows a NW - SE course, its source is west of Alice Springs and runs towards Lake Eyre, though only in very wet years does it join up with the waters of the Macumba to actually reach Lake Eyre. Which is perhaps a good thing because the narrow gauge line crossed the Finke River, as shown in the view below. Originally the track bed was laid on a low level formation across the river bottom, but due to the consequences of damage and delays caused when the river did run with any volume a low concrete bridge was constructed in about 1961. In the view below an NSU powered train uses the original formation, with the new bridge in the background.


Other Australian Sulzers:
Commonwealth Railways NT Class

The link below points to a video clip showing the method used to dismantle the southern part of the narrow gauge line. The clip features one of the NSU class locomotives, and if you listen carefully the rhythmic beat of the Sulzer six cylinder engine can be heard......enjoy
The end of the Narrow Gauge


Over the hills and far away.........to Broken Hill, NSW.
The narrow gauge NSU & NT diesel electric locomotives were the only Sulzer powered locomotives to operate in Australia. However there were other types of installations operating Sulzer diesels in and around Australia. 284 kilometers east of Peterborough SA is the mining town of Broken Hill NSW which in the early 1930's become the home of a very large power generating plant.
The discovery of the silver-lead-zinc mineral deposits in the area around Broken Hill, New South Wales in the 1880's saw the arrival of miners to work these deposits. During May 1908 two seven inch Sulzer turbine pumps were brought online at the new mill of the South mine. By the 1920's there were nine mines working the 'Line of Lode' with most using steam to power generators, with the electricity used in all areas of the mine operations. Like many of the steam railway operations in parts of Australia the mines also suffered from a shortage of water and the lack of local fuel made the steam generation expensive. To overcome this serious problem a new, centralised powerhouse was proposed in 1927, with an electrical output sufficient to handle all the electrical & compressed air needs of the mines. The cost of this electricty to the mines was at a cheaper rate than they could achieve with their own varied and aging installations.
The plant was originally ordered by the Australian Ore & Metal Co Pty Ltd but was later transferred to the Western New South Wales Electric Power Pty Ltd which would oversee the construction and operation of the plant, with Sulzer Brothers being one of the successful bidders. Six two-cycle engines, each developing 2,900hp were direct coupled to British Thomson-Houston, Rugby built 2,500 kva flywheel generators producing three-phase current of 40 periods and 6,900 volts. Additionally there were four Mirrlees, Bickerton & Day diesel engine driven compressor sets, each of 1,230hp, for supplying compressed air. The switchgear and electrical accessories were contracted to the Australian General Electric Comany, Melbourne.
During November 1930 the first engine and generators arrived at Broken Hill, having been shipped through Port Pirie. Their erection was under the supervision of Messrs J Treichler, chief erector for Sulzer Bros, Switzerland & his assistant J Mueller. The erection of the first engine would take about four months. The other engines would arrive at monthly intervals, with the second engine expected to arrive by the end of November 1930.
On July 18th 1931 the plant took over the continuous electrical load of the mines of the North Broken Hill Ltd, Broken Hill South Ltd, Broken Hill Ltd and Zinc Corporation Ltd. No serious incidents were reported during the first six weeks of operation. After installation a continuous trial of 20 days was successfully completed. Normal output would amount to 22,300hp, but with the ability to run at 20% overlead for short periods, thus providing a maximum output of 27,800hp.
When the Broken Hill plant came online it replaced the power station in Shanghai, China as the world's largest diesel engined power station.

A view of the six Sulzer engines in Station A. These were of the 6Z65 crosshead-type two stroke, each of 2,900bhp at 160rpm, 650mm bore & 880mm stroke. They were originally built with blast injection but were later onverted to airless injection during the 1940s & 1950s.
In 1938 a seventh Sulzer engine was added, being a 6ZD65 crosshead-type two stroke, producing 3,200bhp at 160rpm. This engine had the same bore & stroke of the earlier 6Z65 type, but was equipped from new with airless injection.
Increased growth of the mines following World War II led to a major expansion for the Central Power Station, at a proposed cost of £2 million. The output of the existing station was already the largest in the Southern Hemisphere, with completion of the expansion in 1951 it would rank as one of the largest in the world. The new facility, known as Station B would be a replica of the existing Station A. By the summer of 1949 work on Station B and its powerhouse was sufficiently progressed to permit the installation of the first of the four diesel engines and air compressors. These would allow an additional 14,000 cubic feet per minute for use by the mines. Four substantial concrete foundations had been poured, two for the air compressor sets and one for a 3,000kW diesel generator set. Received from England & Switzerland during June 1949 were 500 tons of machinery, including one of the Sulzer engines, weighing 300 tons, from Switzerland and a 3,000kW alternator from British Thompson Houston. With the arrival of this machinery it was anticipated that a trial run would take place in July 1949. The second two would be received during May/June 1950, with the last shipped from Switzerland late in 1950.
Other work included three cooling towers, a 16 inch compressed air pipeline to the Zinc Corporation and N.B.H.C. mine, a workshop for the A & B Stations, switch room and oil treatment plant. For the employees a change-house and mess facilities were added. When completed the existing capacity of the Central Power Station provided by the Sulzer engines would increase from 20,600bhp to 39,100bhp. Total output for Station A would be 15,800 kW electric power and 4,000 kW air power, Station B 12,000 kW electric power and 2,000 kW air power.
On Monday March 6th 1950 the first of the new engine/generator sets had a satisfactory fifteen minute trial run and was expected to be in regular service by the end of March. The complete weight of the unit was about 300 tons, the alternator weighed 43 tons, the crankshaft 20 tons, the crankcase 27 tons, the cylinder cover 1.5 tons and the connecting rod with top and end bearings weighing about 1.5 tons. A second machine was being readied for service.
The engines supplied during this major construction period were:
1947 - one Sulzer 5TPF48 trunk-piston-type two-stroke of 1,450bhp at 218rpm
1949 - three Sulzer 6SF72 crosshead-type two-stroke, each of 4,150bhp at 185rpm.
During 1953 it was reported that four new engines were ordered from Sulzer Brothers to replace existing engines at the facility. These were part of the installation of three new air compressors, and were to replace the original Mirlees units located at Station A. Work on the new installation at Broken Hill was expected to commence during June 1954. Two of the engines arrived at Broken Hill during September 1953, the others were shipped from Winterthur during October 1953, with arrival at Broken Hill expected during December 1953.
These improvements utilised a Sulzer 6SF72 crosshead-type two-stroke of 4,150bhp at 185rpm and seven smaller Sulzer 4T48 trunk-piston-type two-stroke, each of 1,200bhp at 160 to 218rpm. The addition of these engines brought the total output of Sulzer engines at the facility to 47,050bhp.
By 1984 these nineteen Sulzer engines had accumulated 2,450,213 running hours with the longest running engine having more than 255,000 running hours!
In 1986 a new 40 megawatt generating station was built at Broken Hill to replace the two earlier plants. Once the new plant was on line the older plants were closed and dismantled.

Resources:
Sulzer Technical Review, November 4th 1929
Sulzer Technical Review, Special Number 1933
Railway Gazette, Overseas Railway Edition, 1954.
Railway Gazette, Overseas Railway Edition, 1956 (including map above).
Railway Gazette, Overseas Railway Edition, 1962
Gas & Oil Power, January 1934, pp 6-11
Australia Trove Resource for digitised newspapers and other resources
Information regarding the dismantling of the line: Graeme Reid.
Page added March 18th 2003
Page last updated March 4th 2012.
Return to Sulzer page
Return to Picture menu
Return to Home Page