(Below) Publicity views include two (left & center) taken from an advert from 1935 featuring the first order of Sulzer powered locomotives to Siam, whilst (right) shows No.503 in service at Bangkok.
At least two of these locomotives saw service into the 1990's under the ownership of the Jalan Prathan Cement Company at their Ban Sa plant near Ban Cha-am - Km 203 - on the SRT's southern line. A branch line connected with the station to their plant. The two locomotives were 504 (21828 – 1931) and 505 (21829 – 1931). 504 was noted in a shed, perhaps operational whilst 505 was plinthed near the works office.
January 2008 - 505 remains plinthed in front of the sales office of the cement works. It is located in a garden under some trees, not a photogenic location. Externally the locomotive itself is not in a too bad shape, however it is completely gutted, using it as a conference room... It was advised they do not own 504 anymore, and had been moved to a scrapyard. Information courtesy Patrick Rudin.

The Second World War
As mentioned above one of the original order of the 450hp Sulzer locomotives was destroyed by enemy action during World War II. Although not a statistic to linger over this locomotive probably has the dubious honour of being the only Sulzer powered locomotive destroyed during wartime.
However this individual loss palled in comparison with what the country suffered and the railways in general through actions taken by the Japanese, or the Allied bombing missions.
Twenty two principal station yards and signalling centers were bombed, with several being completely destroyed. Twenty five miles of track were torn up. The railway's primary workshops at Makasan, Bangkok sustained severe damage with over twenty buildings destroyed.
The general rolling stock suffered greatly. Of the 186 steam locomotives on the roster in 1939, 105 suffered damage of some sort, of these 78 would be scrapped. Two diesel electric locomotives were destroyed as were thirteen passenger coaches. Over 50% of the freight wagons were missing, either destroyed or could not be accounted for, some no doubt removed by the Japanese.
However perhaps the greatest loss was the destruction by bombing of 28 steel bridges. The loss of three of these bridges in particular caused tremendous difficulties to the resumption of traffic after hostilities had ceased.
Rama VI Bridge across the Menam Chao Phya
connects Bangkok with the southern line - this bridge consisted of five spans totalling 445 metres, rebuilt to carry the railway line, a roadway and two footways. Reopened to traffic December 12th 1953
Surat (Chulachomkloa) Bridge across the Menam Tapi
on the southern line 633 km south of Bangkok - this bridge consisted of three spans totalling 200 metres, rebuilt to carry the railway, a roadway and one footpath. Reopened to traffic February 16th 1953
Bandara (Paramindhara) Bridge across the Menam Nan
on the northern line 456 km north of Bangkok - this bridge consisted of three spans totalling 262 metres, rebuilt to carry the railway and one footpath. Reopened to traffic March 14th 1953
The original bridges had been designed for an axle loading of between 8.00 and 10.50 metric tons, the new bridges were designed with axle loadings up to 15 metric tons. In each case the foundations of the piers and abutments were reused requiring the bridges superstructure to be kept as light as possible despite the increased axle loadings. This was accomplished by the use of high tensile steel, the allowable stresses permitted were much higher than those offered by the use of heavier mild steel. The cost of rebuilding the three bridges totalled Thai Baht 54,486,722.
By January 1946 traffic was able to resume on all lines, made possible by work carried out by railway workers and with assistance from British military forces. Temporary bridges were constructed at Rajburi & Bandara. For the larger bridges at Rama VI and Surat ferries were brought into operation with quays built from pontoon and bailey bridge units. The ferries were capable of handling one locomotive or two freight cars. The temporary facilities would remain in place until new bridges were installed in 1953, as detailed above.
The lack of materials meant that repair work could not be completed as quickly as possible, fortunately rolling stock made surplus by the end of wartime activities provided the opportunity for the Thailand railways to make temporary progress in meeting traffic demands. This surplus stock included 68 steam locomotives and 675 bogie freight cars obtained from the USA, India & Malaya. This stopgap measured allowed the railway to meet increasing demand pending more permanent solutions. By 1950 long term rehabilitation projects were returning the railway to its prewar condition and by 1953 the following were ordered or in the process of being delivered:
70 2-8-2 steam locomotives from Japan
30 4-6-2 steam locomotives from Japan
18 Davenport diesels of 500hp from the USA
4 diesels of 735hp from Switzerland
3 diesels of 960hp from Switzerland
260 passenger carriages from Japan
1,000 four wheel covered goods wagons from Japan
220 low sided wagons from Belgium
10 bogie water tanks from Japan
Materials to rebuild and update Makasan Workshops
36,700 metric tons of 60lb rail from the USA & the United Kingdom
1,100 sets of turnouts (points) from the USA, United Kingdom & Japan
Steel bridge spans from Japan to replace 25 bridges.
Total estimated cost of the refurbishment was Thai Baht 537,000,000, of which 47% went to rebuilding the infrastructure - permanent way, bridges, buildings etc.

Bo-Bo 735hp locomotives of 1945/46 delivery
651 - 654
For the longer and heavier graded southern mainline from Bangkok to Singpore (750 miles) & the northern mainline from Bangkok to Chieng Mai (470 miles) the RSR looked for more powerful locomotives. The good service record of the first order of Sulzer powered locomotives led to the placing of a further order with Sulzer Brothers.


Sulzer were able to provide a more powerful engine in this second order (430hp v 735hp), and were able to construct the locomotives using newer weight saving methods, allowing for the use of only four axles to carry the locomotive weight, rather than six axles as in the first order. The mechanical portion was built by Henschel & Sons, Kassel, the electrical equipment by Ateliers de Construction Oerlikon, whilst Sulzer, Winterthur built the power unit.
The 6LDA25 power unit was a six cylinder four stroke machine of conventional Sulzer construction. Cylinder diameter was 250mm, piston stroke was 320mm. The one hour output rating 735hp at 850rpm, continuous rating was 650hp at 750rpm. Tractive effort was 9,200lb at 17.5mph (one hour rating) or 6,800lb at 22.5mph (continuous rating).

The heart of the machine, the Sulzer 6LDA25 looking towards the radiator end of the locomotive.
The outward appearance of the 1945/46 deliveries differed somewhat from that of the 1931/32 order. Weight saving was achieved by replacing standard rolled sections with bent sheet metal parts riveted or welded. Much welding was used to create the main structural members and the bogie frames. For instance the horizontal middle and upper transoms, when fabricated using the latest procedures were forty percent lighter with a sixty five percent higher bending resistance.
One major design change from the first order was the position of the intakes for receiving air for the traction motors. In the first order the cooling air was drawn from underneath the locomotive body. This location caused inordinate amounts of dust to be drawn in causing serious operating problems for the traction motors. For the second order air was drawn in from the region of the cab roof, which also provided for improved air circulation within the cabs.
Termite damage to the wooden surfaces in the cabs was mitigated through the use of impregnated plywood or teak.
Testing of the first locomotive took place in June 1942 over the Rhaetic Railways hauling loads up to 182 tons. Delivery to Siam did not begin until hostilities ended in 1945.
 | A view of one of the second order of locomotives for Thailand, seen here under test in Switzerland - this view being used to advertise Sulzer powered diesel locomotives and railcars. As usual the locomotives of this period sport a quite considerable builder's plate, mounted midway along the side of the locomotive. |
These four locomotives ended their days working the Maeklong line, most definately 651 & 654, probably lasting in service until about 1989.

Photograph courtesy Robert M. Boer of Rail Asia
Some forty years after delivery 651 was still operational and photographed in a corner of the Mahachai depot on March 23rd 1986.

A1A-A1A 960hp locomotives of 1951 delivery
561 - 563

During 1951 three locomotives were delivered to the Royal State Railways of Siam for use on routes between Bangkok & Padang Besar (625 miles) and Bangkok & Chiengmai (465 miles). Gradients on the southern mainline are at a ruling 1:100 with short distances of 1:50, curve radii vary from 590ft on the main line to 510ft on sidings and through points. The maximum axleloading was 12 tons, maximum speed limit was 40mph. Temperatures varied between 50F & 104F, with a maximum altitude of 2,000ft. On the northern line gradients were more severe with stretches of 1:42 & 1:37. Trailing loads were 420 tons over the southern route and 250 tons on the Chiengmai line.
With Sulzer Brothers Ltd again as the main contractor all specifications were to their requirements, electric transmission equipment was provided by Maschinenfabrik Oerlikon, the mechanical portion completed by Henschel & Sohn GMBH. Particular attention was paid to the maximum axle load requirement, the A1A-A1A wheel arrangement being preferred after much study. In order to simplify matters for the Siam railway authorities much standardisation took place between these units and the earlier 735hp Bo-Bo machines. Although more cylinders were involved in the newer engines many of the components were of the same dimensions. The electrical control equipment, driving controls, wheel centres, tyres, axleboxes, springs, brake blocks and other mechanical portions were the same as were the basic lines of construction.

The power unit was a Sulzer pressure-charged 8LDA25 type set to give 960hp at 850rpm at the one hour rating, or 860hp at 800rpm continuous rating, cylinder dimensions were 9.85in by 12.6in (250mm x 320mm). It was of the usual welded construction of cylinder block, crankcase & bedplate made up of mild steel & cast steel components. Dry weight for the engine was 18,240lb. Charge air was provided by a Sulzer exhaust gas turbo blower with the usual plain bearings for the shaft.
The Oerlikon main generator was mounted on the common welded steel subframe. Continuous rating was 800rpm, 1,000volts, 550amps or 800rpm, 630volts, 860amps, the one hour rating was 800rpm, 497volts, 1070amps, the maximum rating was 850rpm, 1060volts, 1680amps. The auxiliary generator, of 33.7kW is of the overhung typeand supplied the main generator excitation current; motors for the cooling water pump, radiator fan, exhauster, air compressor, rotary voltage converter and for charging the batteries.

The four traction motors were self ventilated and nose suspended, grouped in parallel. Each motor was rated at 121.5kW, 268amp, 497volts, 700rpm - one hour rating, or 125.5kW, 215amp, 1000rpm, 630 volts - continuous rating. Ventilating air was drawn in from behind the cabs
A Sulzer automatic field regulator control allows the driving controller to regulate the engine governor, setting the engine speed at predetermined values; the main generator excitation provides a constant torque on the engine. Eight speed-torque loadings are available from 470 to 850 rpm and from idling to 960hp. Overloading is prevented in all circumstances, shutdown will also occur if cooling water or lubrication oil pressures fail or become too high.
The low required axle loading led to the complete welding of the locomotive body, bent and pressed sheet steel were used for all horizontal & vertical parts, providing much additional stiffening to the framework. The complete body framework is welded and riveted to the underframe.
The bogie frames were completely welded and supported on SKF roller bearing axleboxes through overhung laminated springs. Each bogie carried one brake cylinder, each motored axle had two brake blocks per wheel, connected through compensated rigging.

Trial runs on the Rhaetian Railway provided some interesting data, not only because of the steep grades (up to 1 in 25) combined with sharp curves but because this was a locomotive built for a tropical climate under test in winter conditions. Runs were made first between Landquart and Ilanz, 26 miles with an average grade of 1 in 200; and with a ruling grade of 1 in 100 for five miles, curved almost throughout at 262ft - 985ft radius. Trailing loads up to 300 tons, were made up of sixteen bogie coaches; on the 1 in 100 grade with the curves a sustained speed of almost 27mph was maintained, the diesel engine working on its one hour output. On the Ilanz route grades of 1 in 72 with curves of 262ft radius were featured. Landquart is at 1,730 ft, Ilanz is at 2,300 ft. Fuel consumption for the return trip was equivalent to 0.021lb per gross ton-mile.
Further trials conducted over the 13.25 miles between Landquart & Kublis, rising all the way at an average of 1 in 69 and with a ruling grade of 1 in 25, were run with 155 tons trailing. Speed up the ruling grade was 25mph at the beginning but fell to 13mph after 0.62 mile with the controller on notch 9, equal to the diesel engine continuous output. Fuel consumption on the Landquart - Kublis section was 0.033lb per gross ton-mile.
Dimensions for the Bo-Bo & A1A-A1A locomotives
|
1931 A1A-A1A |
1946 Bo-Bo |
1951 A1A-A1A |
| Weight, empty/full | ??/60tons | 43.5/46.5tons | 54/58tons with 2,700 litres of fuel |
Minimum adhesion weight | 43tons | 44.5tons | 44tons |
Maximum Axle Loading | ?? | 12 tons | 12 tons |
Starting Tractive Effort | 20,680lb | 20,000lb | 30,900lb |
Tractive Effort - Continuous | ?? | 6,800lb @ 22.5mph | 12,800lb @ 19mph |
Tractive Effort - One Hour | 9,130lb @ 12.8mph | 9,200lb @ 17.5mph | 17,600lb @ 14mph |
Tractive Effort - Full Power & Max Speed | ?? | ?? | 6,600lb @ 40mph |
Wheel Diameter | 36in -driving, 30in carrying | 3.00 ft | 3.00 ft |
Bogie Wheelbase | 9ft 10in | 7ft 10.5in | 9ft 10in |
Distance between bogie pivots | 24ft 3in | 22ft 7.375in | 25ft 7in |
Length over buffer beams | 44ft 6.75in | 37ft 1in | 42ft 0in |
Maximum width | ?? | 9ft 1.5in | 9ft 2in |
Maximum height | ?? | 12ft 6.25in | 12ft 6.5in |

The following is an extract from the Diesel Railway Traction journal, July 1951 detailing additional testing of one of the locomotives awaiting shipment to Siam
Testing of one of the new diesels over the Rhaetian Railways Landquart-Klosters-Davos route included operation under severe winter weather conditions. In fact the day after testing the route was blocked for a week due to heavy snowfall & avalanches.
Timings and loads of these recent test runs were adjusted so that the continuous output, at least of the diesel engine should be required more or less all the way from Lanquart to Davos-Wolfgang, a 44km (27.5mile) metre gauge route entirely uphill, with ruling grades of 4.5 & 4.52 percent (1 in 22), with one 800 metre stretch of 5 percent (1 in 20) just south of Klosters. Throughout the steepest grades there is a constant succession of curves of 100 to 300 metres radius. Between Klosters & Davos the 1 in 22 grade, with the 1 in 20 section also, extends continuously for 10km (6.2 miles) with only the intermediate platform lengths as intervening levels sections.
On controller notch 10, corresponding to the one hour diesel engine output, speed was 34kph (21.1mph) at the beginning of the 1 in 22.25, and fell to 32-33kph (19.8-20.5mph). Using controller notch 9, corresponding to the continuous output of the diesel engine the speed maintained over the same section was 30.5-31kph (19.5mph). Trailing load was three bogie coaches weighing 60 tonnes. From Landquart to Kublis, with a maximum grade, short in length, of 3.46 percent (1 in 29) trailing grade, the load was eight bogie coaches weighing 157 tonnes. From Kublis to Kosters with 4.26 to 4.37 percent (1 in 23.5 to 22.75) grades, trailing load was four bogie coaches weighing 80 tonnes; and from Klosters to Davos-Wolfgang with continuous 1 in 20 to 1 in 22.25 grades, three coaches weighing 60 tonnes were hauled. Between Landquart & Klosters the electrical equipment was loaded slightly above the continuous rating; and on the Davos - Wolfgang route the throughout average load was just equal to the continuous rating.
Test run of 960hp Sulzer diesel locomotive
| Station |
Time |
Distance - km |
Height above sea level in feet |
Max Grade |
Sustained speed - mph |
| Landquart |
dep 9.10
|
0.0 |
1,725 |
1 in 25 |
21 |
Kublis |
arr 9.51 - dep 9.55
|
21.5 |
2,665 | 1 in 23.5 |
21 |
Klosters |
arr 10.28 - dep 10.30
|
32.5 |
3,910 | 1 in 23 |
21 |
Davos-Wolfgang |
arr 10.54
|
43.6 | 5,330 | 1 in 20 |
19.2 |
The Rhaetian Railways imposed the following speed limits on this route:
Landquart - Kublis: 55/65kph (34/40.5mph)
Kublis - Davos: 40/42kph (24.8/26mph)
In general the diesel engine was developing 850 - 950hp from Seewis to Davos-Wolfgang (23 miles).
Fuel consumption over the return trip between Landquart & Davos-Wolfgang was 11.3gr per tonne-km (0.045lb per gross ton-mile). The trials were of exceptional interest not only because of the sound behaviour in heavy snow conditions of a locomotive designed for tropical service, but also because of the way steady speeds of 18.5 to 21mph were maintained up gradients exactly twice as steep as the maximum to be encountered in Siam, and at heights up to 5,330ft above sea level at Davos.

A locomotive from the 1951 order on test in Switzerland.

A report from 1960 indicates that all of the locomotives from the second & third order were in service as part of Siamese State Railways fleet of sixty five diesel locomotives. Three pre-war diesels were included in these totals, presumably this must include the two remaining locomotives from the first order.

Sources:
Railway Gazette, August 7th 1931, Diesel Railway Traction April 1946 & February 1951.
Sulzer Technical Review, Special Number 1933
Railway Gazette, Overseas Edition 1951
Railway Gazette, Overseas edition, 1954
The Railways of Thailand - Roel Ramaer, White Lotus, Bangkok 1994.
Page added April 21st 2003
Page updated October 23rd 2010
Return to Sulzer page
Return to Picture menu
Return to Home Page