
Summer of 2007
Although iron ore production at the Marampa mine had long since ceased the mine area still held something of value. The sixty years of activity at the mine had produced tailings, estimated at 50 million tons, located in a number of tailing dams at Marampa. Whilst the tailings contained iron ore, when the ores were originally mined either the refining processes could not retrieve all the iron available within the ore or the cost of doing so was uneconomic at the time in relation to the market price of the refined ore.
During July 2007 the Marampa tailings were tested at the request of the London Mining PLC. Using a modern refining process the tailings were able to yield a product containing 66% iron at a recovery rate greater than 80%. A pilot plant set up to further test the tailings supported the original findings. With an annual estimate of processing three million tons of tailings per annum the production would run for approximately six to seven years. The considerable volumes involved led to the possibility of the processed ore being shipped from the Marampa mine site to the ship loading facilities at Pepel using the existing railway infrastucture, after repair and refurbishment. With this in mind, late in August 2007 London Mining PLC signed a Memorandum of Understanding with the Government of the Republic of Sierra Leone for the lease of the railway line from the Marampa mine to the Pepel port as well as the Pepel port and its facilities.
Although the Sierra Leone Government would oversee the fixed rail and port facilities, London Mining PLC would be responsible for the cost of repairing and refurbishing these facilities. The assets which were to be transfered to London Mining PLC including the locomotives, rolling stock, scrap metal and approximately 60,000 tons of iron ore fines concentrates at Pepel. Further interest in the railway and the port facilities were shown by African Aluminium Ltd (bauxite mining) and African Minerals Plc (diamond & iron mining), development which was welcomed by London Mining in order to share the costs.
At the site of the Marampa Works all the derelict buildings and concrete structures were levelled, whilst the main office building was to be repaired complete with a refurbished roof. The review of the 84km railway line found issues with the original 187,000 sleepers and the 748,000 Pandrol clips that secured the rails to the sleepers. Items missing included 707 meters of rail, 46,000 sleepers, 406,000 Pandrol clips, 3,000 fish plates, 6,000 nuts and bolts and 12,000 washers. The vast majority of the rails that remained in place were generally in good condition having been installed a year before the line closed. However approximately 5,000 meters of rails did require replacement. It was also noted that in four places derailment damage was visible on the sleepers. Other permanent way projects were related to clearing and restoring various structures (bridges, culverts etc) along the route after years of neglect and uninhibited growth of trees and other vegetation. One major part of the trackbed restoration was the requirement of up to 20,000 tons of ballast which would be available from mothballed quarries along the line or from active quarries at Port Loko and Freetown.
Consideration was also given to repair of the facilities at Pepel along with the refurbishment of certain rolling stock located at Pepel. This included:
One shunting locomotive,
Three ballast wagons,
One railway car with trailer,
One flatbed wagon,
One brake van/caboose,
One tanker wagon.
Also present at Pepel were seventeen ballast wagons in reasonable condition and ninety iron ore wagons loaded with iron ore concentrate.
More ominous was the identification of all scrap metal at Pepel - this would no doubt be the end of the carcases of the BRCW/Sulzer diesels abandoned and partially dismantled so long ago.
One of the first commitments was to repair and upgrade the Shengbe Bridge to allow road and rail access.

March 2008
Developments into early 2008 involved a study of the railway recommending the line retain its 3ft 6in (1,067mm) gauge which would provide a capacity of just over 10 million tons per annum. During April 2008 Dr Ernest Bai Koroma, the President of the Republic of Sierra Leone officially opened the refurbished joint railway/road bridge near Pepel.
A report produced for the government of Sierra Leone by UK based railway engineering consultants Scott Wilson Railways took a detailed look at the operating capacity of the line with regard to its use by multiple users. Using one (existing?) 2,000hp locomotive 25 wagons carrying 1,100tons of concentrates could be hauled along the existing railway track. After refurbishment and with one passing loop six train sets could provide nine services a day, six days a week, with an annual capacity of just in excess of three million tons per annum. By adding passing loops and doubling train lengths would increase annual capacity to 10 million tons per annum. Increasing axle loadings, conversion to 4ft 8˝in (1,435mm) standard gauge and using 3,000hp locomotives would result in greater capacity but with a major increase in costs related to gauge conversion and re-engineering of the route for heavier trains with higher axle loadings. The Scott Wilson Railways report recommended retaining the current narrow gauge line.
Part of the costs of the Scott Wilson Railways study had been shared by African Minerals Ltd, a Cayman Islands-registered company who early in May 2008 entered into an exclusive Memorandum of Understanding (MOU) with the Government of Sierra Leone to complete a study with regard to converting the railway line from narrow gauge to standard gauge! Following the study it would upgrade the line, maintain it and operate it on a commercial basis.
London Mining PLC began investigating the validity of African Minerals’ announcement and its own Memorandums of Understanding with the Government of Sierra Leone. Although the concerns from the two companies had much validity the concerns when they were narrowed down were minimal. London Mining PLC's license primarily involved the mine at Marampa and a specified area around the mine. African Minerals license was more extensive, their surveys covered over half of Sierra Leone and included land in the vicinity of the Marampa mine. Their surveys discovered that the iron ore deposits in the Marampa area were more extensive than first thought and extended beyond the geographical limits of the London Mining license. To whatever extent these boundary claims were legitimate (the differences between lines drawn on maps versus markers on the ground) the conflict was resolved leaving London Mining to go about its business at the Marampa mine and African Minerals to handle to bauxite operation in the Port Loko area.

October 2009
A look at satellite images of the Pepel area still reveal much of the infrastructure from the iron ore activities. The main locomotive repair shed is clearly visible including the intact BRCW locomotive in the yard. To the south towards the ship loading gantries are several long lines of ore wagons. The route of the line can be followed for many miles but several section of the satellite imaging are of poor quality, including the Marampa area.

November 2009
The following views were taken on a brief visit to Pepel on November 2nd 2009. The photographer, Richard, had spent many of his childhood years in Sierra Leone, his parents being missionaries in the Freetown area. The growing civil unrest had caused the family to leave during 1995. As stability returned to Sierra Leone the family looked for the opportunity and timing to make a return visit. When this took place in October/November 2009 one of the items on the list of things to do was to visit Bunce Island, an important location used in the processing of slaves for transport to the British colonies in America.
To reach Bunce Island it was necessary to charter a small boat from Freetown, Bunce Island is also very close to the port & railway facilities at Pepel. With an interest in railways Richard couldn't pass up the opportunity to be dropped off on Pepel Island to visit the facilities! The photographs below are taken from his very brief visit. A motorcycle taxi was used to get him from the drop-off point to the facilities, then a hurried dash to see as much as possible before a quick return to the boat, where the boatmen and Richard's family were patiently waiting, still with an hour's journey back to Freetown and with the afternoon light drawing in.
 |  |  | Three views of the loading facilities at Pepel, November 2nd 2009. |
The three views above show the two oreloading gantries at Pepel. These can be compared with views found earlier on the page, particularly the view of the Hindpool. The right view shows both oreloading gantries. The nearer one is the shorter one seen in the left photograph from the shore with the abandoned boat, whilst the more distant gantry, with two loading points also features in the center view taken from the shore. The umbrellas provided to the passenger (for the rain or sunshine?) are all imprinted with images of US President Obama.
 |  |  | Three views of the locomotive servicing & repair facilities at Pepel, November 2nd 2009. |
The three views above show the shed yard and inside the shed. The left view looks towards the servicing & repair facilities, to the right is perhaps one of the original iron ore wagons which has now been modified for other purposes (ballast work?). The center view looks back from the shed entrance across the yard to the location of the left view. The upturned metal components in the right of the photograph appear to be fuel tanks from one of the Alco locomotives. The right view show No.203 gathering dust, but seemingly pretty much intact and awaiting its next call to duty. Will this ever come? Behind No.203 are the two shunters and out of view to the right, just inside the shed is Alco No.204.
These shed views suggest some sort of tidy up has taken place. The BRCW/Sulzer storage shed has been moved (scrapped?), the shunter No.151 has been placed in the shed and the area generally cleaned up of junk. Richard's time in this area was brief, but from the views taken it appears that possibly all the scrap equipment previously to be found in the surrounding areas amongst the bushes and trees is now gone.
 |  |  | Three miscellaneous rolling stock views at Pepel, November 2nd 2009. |
When operations finally ceased on the railway it appears that the vast majority of the rolling stock was returned to Pepel for storage or disposal. The three views above show the resting places of many of the wagons, many of which have probably not turned a wheel in twenty five years. The left view, looking northwards shows the primary location for the storage of the iron ore wagons, situated in the main yard south of the guard shack/radio tower and north of the power house. When the wagons were abandoned many were loaded with ore, over the years these wagons are now sprouting a fine growth of grass! The center view, looking southwards shows the yard where all the wagons are dumped, included in these storage lines are a number of the original wagons from the 1950's. Barely visible on the extreme right are a set of lines almost lost in the dirt. These lines drop down into the lower area, and are believed to be shown in one of the black & white views above with the train drawing up the incline. The right view, looking north towards the guard shack and supply buildings, show the north end of the yard and the base of the radio tower. Two cabooses are visible in this view, whilst a third is barely visible in the far distance next to the corrugated supply building.
 |  |  | Three miscellaneous views of the facilities at Pepel, November 2nd 2009. |
The left view shows the empty office/administration building as viewed from the river channel. To the right is the short loading gantry, behind this was the original storage area for the ore awaiting trans-shipment from the railway to a ship. Just visible at the base of the large building is a large ancient cannon pointing out to sea. The new sign above the abandoned boat reads 'African Mining, Pepel Port & Rail Project.' The security guards at the facility were provided by African Mining. The center view, looking north shows the building containing all the power equipment. To the left runs one of the conveyors which connects with the main stockpile of ore. When the facilities were abandoned about 60,000 tons of processed ore remained at Pepel, either in the stockpile area or in many of the railway wagons. The right view shows part of the stockpile and one of the giant wheel buckets used to handle the ore pile.

2009/2010
London Mining PLC
The mining licence acquired by London Mining in 2006 provided for production of 1.5million tons per annum from the existing tailings at Marampa. An additional 1.5million tons per annum could also be obtained from the hard rock portion of the resource. If all that is necessary to commence mining falls into place London Mining would modify the shipping route to be taken by the ore. Trucks would convey the ore for the first 40km using new and existing roads, it would then be taken 60km by barge to floating cranes which would hand it over to ocean going vessels.
African Minerals
As mentioned earlier the concession granted to African Minerals for the exploration of parts of Sierra Leone carried the risk that nothing of any significance might be found with no viable return on the expenses incurred. On the other hand risk taking can have its rewards and it appears African Minerals have certainly hit paydirt with regard to the discovery of extensions to the iron ore bearing strata in the Marampa area and the huge find at Tonkolili in the Sula Mountains Greenstone Belt east of Marampa. Initial drilling suggested reserves of five billion tons of high quality concentrate grading in excess of 68% iron at a mass recovery of over 30%. Further extensions of the drilling suggests total reserves may exceed 10 billion tons.
Shipment of this ore would require the building of a 190km heavy haul railway from Tonkolili to a new deep water port to be constructed at Tagrin Point. An initial study of the route for the railway suggests no major engineering issues. The planning strategy also called for the refurbishment and renewal of the Pepel Port and Pepel – Marampa railway system to support the potential to ship hematite concentrate and create an early cash flow for the company.

Well its amazing what you find on Ebay, in the autumn of 2003 a drivers operating manual for the BRCW's came up for bid, having pretty much outlived the diesels it was meant to explain.
It is publication # A11136 dated June 1955 (first edition) with 32 pages. It has some lightly pencilled notations amongst the pages, particularly concerning the operation of certain components.
Shown below are the inside front cover and a schematic of the driver's controls.



Sources
Diesel Railway Traction, March 1955 & Railways of North Africa, John R Day, 1964.
Moydow Mines International Inc. September 23rd, 2005 Port Loko Bauxite Project 1.
London Mining PLC quarterly operations report dated September 30th 2007 & March 30th 2008.
African Minerals Interim Report June 30th 2009.
Page added February 11th 2002
Page last updated January 19th 2010.
Return to Sulzer page
Return to Picture menu
Return to Home Page